Commissioning a house in Latvia: documents and steps
The house is built, but the law does not yet allow you to live in it. First, the municipal building authority (būvvalde) has to accept the building for use. In Latvia this is called commissioning — nodošana ekspluatācijā. In this article we explain which route applies to your house, which documents the law requires and where the process most often gets stuck. Everything has been checked against the Latvian legal texts on likumi.lv.
- A building may not be used until it has been accepted into service. Using a group 2 house before that can lead to a warning or a fine of up to 250 fine units (€1,250) for a private person.
- The route depends on the document you started construction with: a construction notification, an explanatory memorandum or a building permit. The Building Regulations contain a separate list of documents for each route.
- On the explanatory memorandum route, the building authority marks the works as completed within 10 working days. On the building permit route, it sets the acceptance date no later than 10 working days after the documents are submitted.
- If you built the house yourself as a self-builder (būvētājs — a person who organises and takes part in the works for their own needs), no construction log is needed. Instead, a group 2 residential house needs an electrical installation test and an inspection report for heating, chimneys and ventilation. Like every new building, it also needs a temporary energy performance certificate.
- If the new house stands on your own land, the construction application filed with the building authority also counts, by law, as the application to the Cadastre and the Land Register. The building is registered after it has been accepted into service.

What commissioning means
Commissioning means that the building authority checks the finished building and its documents and confirms that it may be used. The Construction Law places this duty on the person who initiated the construction (usually the owner): after the works are finished, they arrange a survey of the building's position and accept the building into service.
«Būvi aizliegts izmantot līdz tās pieņemšanai ekspluatācijā, izņemot šā panta trešajā un 3.¹ daļā minētos gadījumus.» (It is prohibited to use a structure until it has been accepted into service, except in the cases referred to in Paragraphs three and 3.¹ of this Section.)
Construction Law (Būvniecības likums), Section 21, Paragraph two
The exceptions concern buildings that were already in service and are now being rebuilt or renovated, and buildings that are built in stages. In both cases, use during the works must be assessed in the building design. For a new private house these exceptions usually do not apply.
The law sets penalties for using a building before it has been accepted into service. For a private person this is a warning or a fine:
- group 1 building (for example, a single-storey outbuilding with a footprint of up to 60 m²) — up to 15 fine units (€75);
- group 2 building (for example, an ordinary two-storey private house) — up to 250 fine units (€1,250);
- group 3 building — up to 400 fine units (€2,000).
One fine unit equals €5.
What this means for you: commissioning is not a formality. Until it is done, the house is legally not ready to live in.
Source: Construction Law, Section 21, Paragraphs one, two, three and 3.¹, and Section 28, Paragraph two; Administrative Liability Law, Section 16, Paragraph two; General Building Regulations (Cabinet Regulation No. 500), Annex 1.
Which route applies to your house
Before construction, one of three documents is filed with the building authority. It is called the construction intention document. The same document determines how the house is commissioned. If you do not know which document you had, you can see it in your case in the Construction Information System (BIS) at bis.gov.lv.
| How construction started | What you submit at the end | What happens next |
|---|---|---|
| Construction notification (paziņojums par būvniecību; for example, a new group 1 residential building or outbuilding) | Confirm completion of the works in BIS and attach the documents — by the deadline stated in the notification | If the works are not finished, the deadline can be extended in BIS. If the works will not start, the notification is cancelled. |
| Explanatory memorandum (paskaidrojuma raksts; for example, a new group 2 single-family house with a total floor area of up to 200 m²) | Part II of the explanatory memorandum with documents | Within 10 working days the building authority checks for unauthorised construction (built without a permit or differently from what was permitted) and marks the works as completed in BIS. From that day the house is accepted into service. |
| Building permit (būvatļauja; for example, a house larger than 200 m² or a two-family house) | A declaration that the building is ready for use, with documents | Together with you, the building authority sets the acceptance date — no later than 10 working days after the documents are submitted. You show the building to the authority. The authority issues an acceptance certificate. The house is accepted from the date of the certificate. |
What this means for you: start by opening your case in BIS. It shows the intention document and the construction deadline, and everything else depends on them.
Source: Building Regulations (Cabinet Regulation No. 529), Paragraphs 7.¹, 7.², 7.³, 156.¹, 157, 160, 161, 167, 171, 172, 175 and 181.

Steps from finished works to the Land Register
- Check your BIS case. Which intention document you have, what the construction deadline is and whether it has expired.
- Finish the works at least to minimum readiness. On the explanatory memorandum route, a group 2 single-family house can be accepted into service if the general construction works and utilities are finished, the façade is finished, the area on the street side is landscaped and at least one living room, a kitchen and a bathroom (toilet and washing facility) connected to the utilities are fitted out.
- Order an as-built survey from a surveyor. It shows where the building and the external utilities (water, sewerage, electricity) were actually built.
- Obtain utility approvals. They are issued by the bodies and companies that issued the technical conditions — for example, the electricity network or the water utility. If there were no technical conditions for a utility, no approval is needed for it.
- Order an energy performance certificate. Commissioning requires a temporary energy performance certificate (a certified expert assesses how much energy the building will use).
- If you built it yourself — order two inspections: an electrical installation test and a technical condition report for heating appliances, chimneys and ventilation ducts.
- Photograph the façades — all that can technically be photographed.
- Submit the documents in BIS and, on the building permit route, agree the acceptance date with the building authority.
- Wait for the authority's mark or certificate. From that day the house may be used.
- Cadastre and Land Register. If the new house stands on your own land, the construction application is also an application to the State Land Service to register the building in the Cadastre and a request to the court to enter it in the Land Register. From 8 January 2027 this will also apply to a house built on land owned by another person (Construction Law, Section 14, Paragraph 1.⁴). The building is registered in the Cadastre after it has been accepted into service, and entered in the Land Register after the cadastral data are registered. If construction was initiated before 5 January 2026 and commissioning had not been initiated by then, this procedure can be requested in BIS if the requirements of the law are met.
What this means for you: the steps look simple, but each one is done by a different specialist, and each has its own waiting time. If one is delayed or an approval is negative, the whole process stops.
Source: Building Regulations, Paragraphs 157, 160.¹, 167 and 168; Construction Law, Section 14, Paragraphs 1.⁴ and 1.⁶, Section 21, Paragraph one, and Transitional Provision 39.

Documents for each route
The Building Regulations contain three separate lists. Not every item on a list applies to every house. Below is how many types of documents are needed in three typical situations where the owner built the house as a self-builder and no design changes were made during construction.
After a construction notification
- approvals of the readiness of utilities for operation from the issuers of the technical conditions;
- as-built survey plan — for a new group 1 residential building, outbuilding or agricultural non-residential building;
- issue date and number of the temporary energy performance certificate in BIS;
- photos of the façades.
The construction log is not on this list.
After an explanatory memorandum
- approvals of the readiness of utilities for operation;
- as-built drawings — if permissible changes were made during the works;
- construction log with the works documentation — if a construction company built the house, not you as a self-builder;
- as-built survey plan — for a new building, and for a reconstruction if the situation on the site has changed;
- issue date and number of the temporary energy performance certificate in BIS;
- if you built a group 2 residential house yourself — electrical installation test documentation and a technical condition report for heating appliances, chimneys and ventilation ducts;
- photos of the façades — for a new building or if the external appearance has changed.
After a building permit
- declaration that the building is ready for use (Annex 14 to the Building Regulations);
- amended parts of the building design — if permissible changes were made during the works;
- approvals of the readiness of utilities from the issuers of the technical conditions and, if needed, approvals of other bodies (for example, if the building is a cultural monument);
- as-built survey plan, including a vertical survey (height levels of the building);
- construction log — if a construction company built the house; construction supervisor's report — if there was construction supervision;
- equipment test reports and acceptance certificates — if required by regulations;
- cadastral survey file — for a new group 2 or 3 building (for a reconstruction — to the extent rebuilt), unless the building is registered under the single procedure described in step 10;
- temporary energy performance certificate — for a new building; for renovation or reconstruction — if energy efficiency measures were carried out;
- photos of the façades — for a new building or if the external appearance has changed;
- if you built a group 2 residential house yourself — electrical installation test and the heating, chimney and ventilation report.
What this means for you: there is one list in the law, but a different part of it applies to each house. It depends on who built the house, whether anything changed during the works and whose land the house stands on. If a document is missing, the building authority does not start the acceptance.
Source: Building Regulations, Sub-paragraph 107.1, Paragraph 120, Sub-paragraph 156.¹1, Paragraphs 157, 167 and 168; Construction Law, Section 19.¹, Paragraph three, Clause 1.
If the building authority does not accept the house
The building authority may not start the acceptance if any body has given a negative approval or if BIS lacks the required information and documents. If the building is not accepted, the authority takes a decision. It lists the deviations found from the design or regulations and the deadlines for correcting them.
Once the defects are corrected, the building is shown to the authority again (building permit route) or the authority marks the works as completed (explanatory memorandum route).
«Ēka vai tās daļa ir uzskatāma par pieņemtu ekspluatācijā ar akta izdošanas dienu.» (A building or part of it shall be considered accepted into service on the date the certificate is issued.)
Building Regulations (Cabinet Regulation No. 529), Paragraph 181
What this means for you: before submitting, check that all documents are in BIS and that what was built matches what was approved. Construction works that do not comply with the building design are, by law, unauthorised construction.
Source: Building Regulations, Paragraphs 162, 162.¹, 178, 179, 180 and 181; Construction Law, Section 18, Paragraph two, Clause 4.
From our practice
In our cases, commissioning is most often delayed not by the building authority but by what has to be collected before submission. The most common reasons the process stops:
- utility readiness approval — in our cases, obtaining it has taken from 9 days to 6 months;
- a negative chimney inspection report — commissioning stops until the defect is fixed, which can take several months;
- what was built differs from what was approved — then it is no longer just commissioning but dealing with the consequences of unauthorised construction;
- the construction deadline in the BIS case has expired.
The number of as-built surveys required can also differ between municipalities. That is why we start by checking the BIS case and manage all specialists in one flow, up to the authority's mark or certificate.
What this means for you: the sooner one person starts managing the process, the fewer months are spent waiting.
Frequently asked questions
Can I live in a house that has not been commissioned?
No. A structure may not be used until it has been accepted into service. Using a group 2 building can lead to a warning or a fine of up to 250 fine units (€1,250) for a private person.
Construction Law, Section 21, Paragraph two, and Section 28, Paragraph two; Administrative Liability Law, Section 16, Paragraph two.
How long does the building authority take to review the documents?
On the explanatory memorandum route, the authority marks the works as completed within 10 working days of receiving the documents. On the building permit route, the authority sets the acceptance date together with you, no later than 10 working days after the documents are submitted. The time needed to collect the documents is not included.
Building Regulations, Paragraphs 160 and 171.
Can a house be commissioned if the interior is not finished?
A group 2 single-family house on the explanatory memorandum route — yes, if the general construction works and utilities are finished, the façade is finished, the street side is landscaped and at least one living room, a kitchen and a bathroom connected to the utilities are fitted out. The rest can be finished later.
Building Regulations, Paragraph 160.¹
Is a cadastral survey needed?
It is not on the document lists for the notification and explanatory memorandum routes. On the building permit route it is needed for a new group 2 or 3 building, except when the building is registered under the single procedure — when the new house stands on your own land and the application to the building authority also serves as the application to the Cadastre and Land Register.
Building Regulations, Sub-paragraphs 156.¹1, 157 and 167.8; Construction Law, Section 14, Paragraph 1.⁴.
Does the builder have to attend the acceptance?
On the building permit route you invite them. However, if the contractor refuses to attend, that is not a reason for the authority to refuse acceptance. The same applies to the construction supervisor.
Building Regulations, Paragraphs 172 and 174.
Want to know what your house is still missing?
Send us the cadastral number or address. Volko Engineering will look at your BIS case and tell you what your house still needs. If you wish, we will handle the commissioning for you — from the first document to the building authority's mark or certificate. We work in English.
Send a request →Prepared by: Vladimirs Volkovs, Chairman of the Board, SIA «Volko Engineering». About us
Sources (official texts in Latvian)
1. Būvniecības likums (Construction Law) — Section 14, Paragraphs 1.⁴ and 1.⁶; Section 18, Paragraph two; Section 19.¹; Sections 21 and 28; Transitional Provision 39 — likumi.lv/ta/id/258572 (version in force from 01.08.2026, checked 06.11.2026)
2. Cabinet Regulation No. 529 of 02.09.2014 «Ēku būvnoteikumi» (Building Regulations) — Paragraphs 7.¹–7.³, 107, 120, 156.¹, 157, 160, 160.¹, 161, 162, 162.¹, 167, 168, 171–175 and 178–181 — likumi.lv/ta/id/269164 (version in force from 01.10.2026, checked 06.11.2026)
3. Cabinet Regulation No. 500 of 19.08.2014 «Vispārīgie būvnoteikumi» (General Building Regulations) — Annex 1 (building groups) — likumi.lv/ta/id/269069 (version in force from 25.09.2026, checked 06.11.2026)
4. Administratīvās atbildības likums (Administrative Liability Law) — Section 16, Paragraph two — likumi.lv/ta/id/303007 (version in force from 01.10.2026, checked 06.11.2026)
This article is for information only and does not replace advice on a specific building. Names of legal acts and quotations are our own translations; only the Latvian text is legally binding. Regulations checked on likumi.lv 06.11.2026.